1. 0.1%
2. 0.2%
3. 0.3%
4. 2%
0.2\%
1. Compute the slack on all events
2. Transfer resources, if necessary, during monitoring
3. Clearly designate a precedence relationship
4. Simplify the crashing plan
Clearly designate a precedence relationship
1. P-R-T-V
2. Q-S-T-V
3. P-R-U-W
4. Q-S-U-W
Q-S-U-W
1. 10 min
2. 20 min
3. 25 min
4. 50 min
50 min
1. 3
2. 4
3. 5
4. 6
5
1. economic order quantity
2. just-in-time production
3. capacity planning
4. product design
just-in-time production
1. 500
2. 2000
3. 1000/√2
4. 1000√2
1000√2
1. 1000 units
2. 2000 units
3. 2800 units
4. 4000 units
2800 units
1. Scheduling of machines
2. Amount of labor to be committed
3. Rate at which production should happen
4. Inventory to be carried forward
Scheduling of machines
1. order 200 frames every time
2. accept 2% discount
3. accept 4% discount
4. order Economic Order Quantity
accept 4\% discount