1.  Operation E in company 1

2.  Operation E in company 4

3.  Operation F in company 5

4.  Operation E in company 5

4
Correct Answer :

Operation E in company 5


Explanation :
No Explanation available for this question

1.  Reduction of 12.3

2.  Increase of 12.3

3.  Reduction of 5.6

4.  Increase of 5.6

4
Correct Answer :

Reduction of 12.3


Explanation :
No Explanation available for this question

1.  The amount of coding done is greater than that of testing

2.  The amount of coding done onsite is less than that of design done onsite

3.  The amount of design carried out onsite is greater than that of testing

4.  The amount of testing carried out offshore is greater than that of total design

4
Correct Answer :

The amount of coding done is greater than that of testing


Explanation :
No Explanation available for this question

1.  40

2.  20

3.  30

4.  50

4
Correct Answer :

30


Explanation :
No Explanation available for this question

1.  Sum of estimated and actual effort for offshore design

2.  The estimated man-hours of offshore coding

3.  The actual man-hours of offshore testing

4.  Half the no. of estimated man-hours of offshore coding

4
Correct Answer :

The actual man-hours of offshore testing


Explanation :
No Explanation available for this question

1.  coding

2.  design

3.  offshore testing

4.  offshore design

4
Correct Answer :

design


Explanation :
No Explanation available for this question

1.  Offshore, design and coding

2.  Offshore coding

3.  Testing

4.  Offshore testing and coding

4
Correct Answer :

Offshore coding


Explanation :
No Explanation available for this question

Interview Questions

MongoDB
Java Script
Node JS
PHP
JQuery
Python