1.  F(t)=sint

2.  F(t)=e-t sint

3.  F(t)=e-t

4.  F(t)=1-e-t

4
Correct Answer :

F(t)=1-e-t


Explanation :
No Explanation available for this question

1.  

2.  

3.  

4.  

4
Correct Answer :


Explanation :
No Explanation available for this question

1.  8.17

2.  11.15

3.  14.14

4.  22.30

4
Correct Answer :

11.15


Explanation :
No Explanation available for this question

1.  0.63

2.  0.32

3.  1.26

4.  1.46

4
Correct Answer :

0.63


Explanation :
No Explanation available for this question

1.  5.94

2.  1.83

3.  7.9

4.  39.5

4
Correct Answer :

7.9


Explanation :
No Explanation available for this question

1.  28.3

2.  42.9

3.  34.4

4.  14.6

4
Correct Answer :

28.3


Explanation :
No Explanation available for this question

1.  A-b-e-g-h

2.  A-c-g-h

3.  A-d-f-h

4.  A-b-c-f-h

4
Correct Answer :

A-d-f-h


Explanation :
No Explanation available for this question

1.  Critical path remains the same and the total duration to complete the prohject changes to 19 days

2.  Critical path and the total duration to complete the project remain the same

3.  Critical path changes but the total duration to complete the project remains the same

4.  Critical path changes and the total duration to complete the project changes to 17 days

4
Correct Answer :

Critical path remains the same and the total duration to complete the prohject changes to 19 days


Explanation :
No Explanation available for this question

1.  516k

2.  532k

3.  484k

4.  468k

4
Correct Answer :

516k


Explanation :
No Explanation available for this question

1.  90.1

2.  56.3

3.  4.4

4.  12.9

4
Correct Answer :

12.9


Explanation :
No Explanation available for this question

Interview Questions

MongoDB
Java Script
Node JS
PHP
JQuery
Python