1. Event
2. Float
3. Duration
4. Constraint
Float
1. Normal
2. Binomial
3. Beta
4. Exponential
Beta
1. Normal
2. Binomial
3. Beta
4. Gaussian
Gaussian
1. Latest start time – earlier start time
2. Latest finish time – earliest finish time (EFT)
3. TL – EFT
4. All of these
All of these
1. Duration
2. Total float
3. Free float
4. Interfering float
Free float
1. Minimum time – required for completion of project
2. Maximum time required for completion of project
3. Maximum cost required for completion of project
4. Minimum cost required for completion of project
Minimum time – required for completion of project
1. Positive value
2. Negative value
3. Zero value
4. Same value
Zero value
1. To concentrate his attention on critical activities
2. To divert the resources from non – critical advanced activities to critical activities
3. To be cautions for avoiding any delay in the critical activities to avoid delay of the whole project
4. All of these
All of these
1. (a + m + b)/6
2. (a + 2m + b)/6
3. (a + 4m + 6)/6
4. (a + 5m + b)/6
(a + 4m + 6)/6
1. Same as at the end point
2. Increasing proportional to that at the end point
3. Decreasing proportional to that at the end point
4. None of these
Same as at the end point