1. 30
2. 50
3. 70
4. 90
90
1. 5 days
2. 0 days
3. 2.5 days
4. 2 days, if its activity durations time is 3 days
0 days
1. Normal time
2. Slow time
3. Crash time
4. Standard time
Slow time
1. Bêta distribution
2. Poisson distribution
3. Normal distribution
4. Binomial distribution
Normal distribution
1. 6 days
2. 1 day
3. 2 days
4. None of these
1 day
1. Time oriented technique
2. Activity oriented technique
3. Event oriented technique
4. Work oriented technique
Activity oriented technique
1. Decision making techniques
2. Technique to determine project status
3. Aids to the decision maker
4. All of these
Aids to the decision maker
1. Would not increase completion time of the project
2. Would increase project completion time, if the amount of delay is greater than free slack
3. Would increase the project completion time, if amount of delay exceeds total slack
4. Would increase project completion time
Would increase the project completion time, if amount of delay exceeds total slack
1. Shortest path
2. Longest path
3. Moderate path
4. None of these
Moderate path
1. 5 days
2. 6 days
3. 7 days
4. 9 days
6 days