1.  Normal time

2.  Slow time

3.  Crash time

4.  Standard time

4
Correct Answer :

Slow time


Explanation :
No Explanation available for this question

1.  Bêta distribution

2.  Poisson distribution

3.  Normal distribution

4.  Binomial distribution

4
Correct Answer :

Normal distribution


Explanation :
No Explanation available for this question

1.  6 days

2.  1 day

3.  2 days

4.  None of these

4
Correct Answer :

1 day


Explanation :
No Explanation available for this question

1.  Time oriented technique

2.  Activity oriented technique

3.  Event oriented technique

4.  Work oriented technique

4
Correct Answer :

Activity oriented technique


Explanation :
No Explanation available for this question

1.  Decision making techniques

2.  Technique to determine project status

3.  Aids to the decision maker

4.   All of these

4
Correct Answer :

Aids to the decision maker


Explanation :
No Explanation available for this question

1.  Would not increase completion time of the project

2.  Would increase project completion time, if the amount of delay is greater than free slack

3.  Would increase the project completion time, if amount of delay exceeds total slack

4.  Would increase project completion time

4
Correct Answer :

Would increase the project completion time, if amount of delay exceeds total slack


Explanation :
No Explanation available for this question

1.  Shortest path

2.  Longest path

3.  Moderate path

4.  None of these

4
Correct Answer :

Moderate path


Explanation :
No Explanation available for this question

1.  5 days

2.  6 days

3.  7 days

4.  9 days

4
Correct Answer :

6 days


Explanation :
No Explanation available for this question

Interview Questions

MongoDB
Java Script
Node JS
PHP
JQuery
Python