1.  At the broadcast long term period levels

2.  At the short term period levels

3.  Work force and inventory at broadest levels

4.  Work force and inventory at the short term period levels

4
Correct Answer :

Work force and inventory at broadest levels


Explanation :
No Explanation available for this question

1.  Is the outcome of the aggregate planning

2.  Drivers the entire production system

3.   Is a high level scheduled that specifies what and products or product modules are to be produced and the time period during which they are to be made

4.  All of these

4
Correct Answer :

All of these


Explanation :
No Explanation available for this question

1.  Determines the overall production plan for the near future

2.  Provides rough time schedule for production of final products

3.  Refer to the `end items` or final products

4.  All of these

4
Correct Answer :

All of these


Explanation :
No Explanation available for this question

1.  Demand forecasts and pending orders

2.  Resource availabilities and capacities

3.  Stock status and inventory information’s

4.  Feed back information on actual shop loads , backlog and leadtimes

5.   All of these

5
Correct Answer :

All of these


Explanation :
No Explanation available for this question

1.  Master scheduling

2.  Aggregate planning

3.  Routing

4.   Forecasting

4
Correct Answer :

Routing


Explanation :
No Explanation available for this question

1.  Production

2.  Material requirements

3.  Tool orders and move orders

4.  All of these

4
Correct Answer :

All of these


Explanation :
No Explanation available for this question

1.  Scheduling

2.  Routing

3.  Master scheduling

4.  Aggregate planning

4
Correct Answer :

Scheduling


Explanation :
No Explanation available for this question

1.  Type of manufacturing – job . Batch, Mass/Flow production

2.  Nature of process involved

3.  Availability of plant, machineries and facilities

4.  Characteristics of the plant, machineries and facilities

5.  All of these

5
Correct Answer :

All of these


Explanation :
No Explanation available for this question

1.  Scheduling

2.  Sequencing

3.  Routing

4.  Aggregate planning

4
Correct Answer :

Sequencing


Explanation :
No Explanation available for this question

1.  the tasks belong to the various jobs

2.  the tasks are performed on the same facility

3.  acts as an aid to determine the scheduling

4.  emphasis is on the economic order

5.  all of these

5
Correct Answer :

all of these


Explanation :
No Explanation available for this question

Interview Questions

MongoDB
Java Script
Node JS
PHP
JQuery
Python