1.  above the level of S

2.  below the level of S

3.  at the level of S

4.  none of the above

4
Correct Answer :

above the level of S


Explanation :
No Explanation available for this question

1.  MRP (Materials Requirements Planning)

2.  BOM(Bill of Materials)

3.  Time phasing

4.  none of these

4
Correct Answer :

MRP (Materials Requirements Planning)


Explanation :
No Explanation available for this question

1.  Planned order releases

2.  Time- phasing of requirements

3.  Provisions for rescheduling

4.  generation of lower level requirements

5.  allof these

5
Correct Answer :

allof these


Explanation :
No Explanation available for this question

1.  difficult items

2.  scarce items

3.  vital items

4.  dead items

4
Correct Answer :

difficult items


Explanation :
No Explanation available for this question

1.  mostly available in indigenous market

2.  cannot be procured easily

3.  of short supply or imported items

4.   allof these

4
Correct Answer :

of short supply or imported items


Explanation :
No Explanation available for this question

1.  buffer stock

2.  reserve stock

3.  safety stock

4.  none of these

4
Correct Answer :

buffer stock


Explanation :
No Explanation available for this question

1.  recorder point

2.  order quantity

3.  EOQ

4.  maximum inventory level

4
Correct Answer :

EOQ


Explanation :
No Explanation available for this question

1.  Q`=S-(X+Q)

2.  Q`=S+(X+Q)

3.  Q`=S+(X+Q`)

4.  Q`=S-(X+Q`)

4
Correct Answer :

Q`=S-(X+Q`)


Explanation :
No Explanation available for this question

1.  N(1+d/v)

2.  N(1-d/v)

3.  N(1+v/d)

4.  N(1-v/d)

4
Correct Answer :

N(1-d/v)


Explanation :
No Explanation available for this question

Interview Questions

MongoDB
Java Script
Node JS
PHP
JQuery
Python