A. 20 days
B. 22 (1/2) days
C. 25 days
D. 25 (1/2) days
Ratio of times taken by A and B = 1 : 3
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes (3/2) x 60 = 90 days
So, A takes 30 days to do the work.
A's 1 day's work = 1/30
B's 1 day's work = 1/90
(A + B)'s 1 day's work = (1/30) + (1/90) = 4/90 = 2/45
=> A and B together can do the work in 45/2 = 22 (1/2) days